PSyngentaExecutive Cockpit

Integration 360 — PMO

The integration cockpit — turning M&A status into an executable cutover plan, workstream by workstream, blocker by blocker, dollar by dollar.

Syngenta · FY25 (modeled)
Top 3 global crop science company
49,000 employees · 12+ US sites · 100 countries
Executive read· the answer, then the moves

Integration is the value and the risk: $121.3M of synergy is still unbanked across 4 in-flight brands at 67% average completion, with 8 open blockers gating the cutover. Clear the critical path and bank the run-rate before the next deal.

4 of 4 headline metrics improving vs prior · still off target: Synergy Realized 4.5% vs 6.0%, SG&A Ratio 16.2% vs 15.8%, EBITDA $3.33B vs $3.50B

Do now — ranked by urgency
  1. 1
    Clear the 8 open blockers on the critical pathAct now
    Why it matters

    Open blockers hold the cutover — and $121.3M of unbanked synergy — hostage across the 4 in-flight brands.

    What's driving it
    • 8 blockers not yet resolved
    • 67% avg integration across in-flight
    • $3573.25M of revenue still integrating
    FYI
    • Blended cost-to-integrate ROI 1.2x
    • Work the Blocker/High rows first
  2. 2
    Blocker: Quoting / CPQ — Lawn & GardenAct now
    Why it matters

    Gates the cohort cutover (and the exit).

    What's driving it
    • due 2026-09-15 · Mitigating
    • Signal: Integration blocker
    FYI
    • Legacy estimator has no API; quote history export blocked on vendor — stalls CPQ cutover.
    • Owner: Revenue Leadership
  3. 3
    Put a 90-day recovery plan on Purchasing / vendor consolidationWatch
    Why it matters

    Purchasing / vendor consolidation is leaking run-rate: $151.59M actual vs $194.9M plan ($-43.3M variance) — it compounds into the forecast quarters.

    What's driving it
    • Purchasing / vendor consolidation variance $-43.3M
    • Program total $418M vs $519.7M planned ($-101.7M)
    FYI

    Owner: Procurement

  4. 4
    Freeze discretionary spend on Lawn & GardenWatch
    Why it matters

    Lawn & Garden is underwater at 1.0x — $45.48M spent against $43.31M realized; halt discretionary spend until capture catches up.

    What's driving it
    • Lawn & Garden ROI 1.0x
    • Synergy target $77.96M vs realized $43.31M
    FYI

    Protect the ≥1.3x deals as the playbook

🤝 M&A: source → integrate → realizeStep 4 of 6 · the 100-day plan to absorb itBrand / M&A 360Org Roll-up 360All journeys
🌐 Enterprise 360 modules· on Integration 360Browse all 31 views ▾
● LiveBuilt forCOO · Integration PMO· what to cut over nextCFO· unbanked synergyBoard / Wind Point· integration is the value & the risk

Faster integration is Pavion's #1 priority — it is where the deal value is created and where it leaks. This view turns "status" into an executable plan: the 4 in-flight brands, their six workstreams, the blockers in the way, and the ~$121.3M of synergy still unbanked waiting on the cutover.

Data backing: integration_workstream (6 workstreams × in-flight brand, % · owner · target) · integration_blocker (severity · owner · due) · integration_econ (budget · spend · synergy) · synergy_track (program plan vs actual run-rate) · brand_cohort (integration %, status)
Brands in-flight
4
mid-integration
Unbanked synergy
$121.3M
target − realized
Avg integration
67%
across in-flight
Open blockers
8
not yet resolved
Cost-to-integrate ROI
1.2x
synergy ÷ spend
$ still integrating
$3573.25M
4 businesses
Per-brand integration scorecard

Where each in-flight brand stands — and the next move

Do this: work the blocker named in each card first; if none, push the lowest-% workstream to its target date.

Syngenta Group China
acquired 2023 · $1256.05M revenue · synergy 74%
In progress
Overall integration82%
ERP / Ledger90%· Done
Customer Master85%· Jul 2026
Quoting / CPQ70%· Sep 2026
Tech Stack / Network88%· Done
Org / Branding95%· Done
Field / Dispatch75%· Aug 2026
Price-book reconciliation: 40 SKUs priced below governed floor; RevOps reviewing. · Revenue Leadership · due 2026-09-20
Bay-area crews not yet on common telematics; minor utilization drag. · Field Ops · due 2026-09-30
Next move: Clear the medium on Quoting / CPQ: Price-book reconciliation: 40 SKUs priced below governed floor; RevOps reviewing. (Revenue Leadership, due 2026-09-20).
Lawn & Garden
acquired 2024 · $887.9M revenue · synergy 55%
In progress
Overall integration60%
ERP / Ledger55%· Nov 2026
Customer Master60%· Oct 2026
Quoting / CPQ30%· Q1 2027
Tech Stack / Network65%· Sep 2026
Org / Branding80%· Aug 2026
Field / Dispatch50%· Dec 2026
Legacy estimator has no API; quote history export blocked on vendor — stalls CPQ cutover. · Revenue Leadership · due 2026-09-15
Chart-of-accounts mapping unresolved for 3 cost centers; revenue still books region-only (Birmingham 45% coverage). · Office of the CIO · due 2026-10-30
Next move: Clear the blocker on Quoting / CPQ: Legacy estimator has no API; quote history export blocked on vendor — stalls CPQ cutover. (Revenue Leadership, due 2026-09-15).
Cropwise
acquired 2024 · $801.27M revenue · synergy 78%
In progress
Overall integration80%
ERP / Ledger85%· Aug 2026
Customer Master78%· Sep 2026
Quoting / CPQ75%· Sep 2026
Tech Stack / Network82%· Done
Org / Branding90%· Done
Field / Dispatch70%· Oct 2026
Tech certs not yet mapped to common dispatch; manual routing in Columbus metro. · Field Ops · due 2026-10-10
Next move: Clear the medium on Field / Dispatch: Tech certs not yet mapped to common dispatch; manual routing in Columbus metro. (Field Ops, due 2026-10-10).
Syngenta Flowers
acquired 2024 · $628.03M revenue · synergy 40%
Early
Overall integration45%
ERP / Ledger40%· Q1 2027
Customer Master45%· Dec 2026
Quoting / CPQ20%· Q2 2027
Tech Stack / Network50%· Nov 2026
Org / Branding70%· Oct 2026
Field / Dispatch35%· Q1 2027
~200 duplicate accounts vs golden record need steward review before billing migration. · MDM steward · due 2026-11-30
Site network upgrade gating SOC failover; waiting on circuit provisioning (vendor lead time). · Infrastructure · IT · due 2026-11-15
Next move: Clear the high on Customer Master: ~200 duplicate accounts vs golden record need steward review before billing migration. (MDM steward, due 2026-11-30).
Workstream heatmap

Six workstreams × in-flight brands

Read across each row for the brand's weak spot; read down each column for the workstream that's stuck enterprise-wide. Tint = status; number = % complete.

BrandERP / LedgerCustomer MasterQuoting / CPQTech Stack / NetworkOrg / BrandingField / Dispatch
Syngenta Group China90%85%70%88%95%75%
Lawn & Garden55%60%30%65%80%50%
Cropwise85%78%75%82%90%70%
Syngenta Flowers40%45%20%50%70%35%
DoneOn trackAt riskBehind
Blocker & risk log

Every thing in the way of a cutover, worst-first

Do this: assign each open blocker a named owner and a date; the Blocker/High rows are the ones holding synergy hostage.

SeverityBrandWorkstreamDescriptionOwnerDueStatus
BlockerLawn & GardenQuoting / CPQLegacy estimator has no API; quote history export blocked on vendor — stalls CPQ cutover.Revenue Leadership2026-09-15Mitigating
HighLawn & GardenERP / LedgerChart-of-accounts mapping unresolved for 3 cost centers; revenue still books region-only (Birmingham 45% coverage).Office of the CIO2026-10-30Open
HighSyngenta FlowersCustomer Master~200 duplicate accounts vs golden record need steward review before billing migration.MDM steward2026-11-30Open
MediumSyngenta FlowersTech Stack / NetworkSite network upgrade gating SOC failover; waiting on circuit provisioning (vendor lead time).Infrastructure · IT2026-11-15Open
MediumSyngenta Group ChinaQuoting / CPQPrice-book reconciliation: 40 SKUs priced below governed floor; RevOps reviewing.Revenue Leadership2026-09-20Mitigating
MediumCropwiseField / DispatchTech certs not yet mapped to common dispatch; manual routing in Columbus metro.Field Ops2026-10-10Open
Lowrecent acquisitionOrg / BrandingCustomer comms on brand transition pending legal sign-off.Integration PMO2026-08-31Mitigating
LowSyngenta Group ChinaField / DispatchBay-area crews not yet on common telematics; minor utilization drag.Field Ops2026-09-30Open
Synergy realization vs plan

$418M realized vs $519.7M planned · $-101.7M variance

Do this: the negative-variance programs are leaking run-rate — put a 90-day recovery plan on each before they compound into the forecast quarters.

ProgramOwnerPlan $MActual $MVariance% captured
P&C insurance consolidationCFO · Treasury$86.62M$86.62M+$0M
100%
Fleet / auto programProcurement$64.97M$64.97M+$0M
100%
Purchasing / vendor consolidationProcurement$194.9M$151.59M$-43.3M
78%
Systems (CRM / ERP / HR)IT · Office of the CIO$129.94M$90.96M$-39M
70%
Real estate / office overlapFacilities$43.31M$23.82M$-19.5M
55%
Integration economics

Is it paying back? Blended 1.2x on cost-to-integrate

Do this: protect the ≥1.3x deals as the playbook; for sub-1x deals, freeze discretionary integration spend until synergy capture catches up.

BrandAcquiredBudgetSpentSynergy targetSynergy realizedROIStatus
Lawn & Garden2024$82.29M$45.48M$77.96M$43.31M1.0xIn progress
Cropwise2024$73.63M$56.31M$75.8M$58.47M1.0xIn progress
Syngenta Flowers2024$64.97M$25.99M$64.97M$25.99M1.0xEarly
Syngenta Group China2023$99.62M$77.96M$116.94M$86.62M1.1xIn progress
Syngenta Crop Protection2022$69.3M$67.13M$108.28M$95.29M1.4xIntegrated
Syngenta Seeds2021$38.98M$36.82M$56.31M$51.97M1.4xIntegrated
Adama2021$30.32M$28.15M$43.31M$38.98M1.4xIntegrated