PGrasim Industries LimitedExecutive Cockpit

Integration 360 — PMO

The integration cockpit — turning M&A status into an executable cutover plan, workstream by workstream, blocker by blocker, dollar by dollar.

Grasim Industries Limited · FY26 (modeled)
India's #1 VSF producer, Top 3 cement
24,000 employees · 0+ US sites · 51 countries
Executive read· the answer, then the moves

Integration is the value and the risk: $151.6M of synergy is still unbanked across 4 in-flight brands at 67% average completion, with 8 open blockers gating the cutover. Clear the critical path and bank the run-rate before the next deal.

3 of 4 headline metrics improving vs prior · still off target: Synergy Realization 4.2% vs 5.0%, EBITDA Margin 18.2% vs 19.0%, SG&A Ratio 10.5% vs 10.0%

Do now — ranked by urgency
  1. 1
    Clear the 8 open blockers on the critical pathAct now
    Why it matters

    Open blockers hold the cutover — and $151.6M of unbanked synergy — hostage across the 4 in-flight brands.

    What's driving it
    • 8 blockers not yet resolved
    • 67% avg integration across in-flight
    • $4466.55M of revenue still integrating
    FYI
    • Blended cost-to-integrate ROI 1.2x
    • Work the Blocker/High rows first
  2. 2
    Blocker: Quoting / CPQ — LivaecoAct now
    Why it matters

    Gates the cohort cutover (and the exit).

    What's driving it
    • due 2026-09-15 · Mitigating
    • Signal: Integration blocker
    FYI
    • Legacy estimator has no API; quote history export blocked on vendor — stalls CPQ cutover.
    • Owner: Ravi Desai
  3. 3
    Put a 90-day recovery plan on Purchasing / vendor consolidationWatch
    Why it matters

    Purchasing / vendor consolidation is leaking run-rate: $189.49M actual vs $243.63M plan ($-54.1M variance) — it compounds into the forecast quarters.

    What's driving it
    • Purchasing / vendor consolidation variance $-54.1M
    • Program total $522.5M vs $649.7M planned ($-127.2M)
    FYI

    Owner: Procurement

  4. 4
    Freeze discretionary spend on LivaecoWatch
    Why it matters

    Livaeco is underwater at 1.0x — $56.85M spent against $54.14M realized; halt discretionary spend until capture catches up.

    What's driving it
    • Livaeco ROI 1.0x
    • Synergy target $97.45M vs realized $54.14M
    FYI

    Protect the ≥1.3x deals as the playbook

🤝 M&A: source → integrate → realizeStep 4 of 6 · the 100-day plan to absorb itBrand / M&A 360Org Roll-up 360All journeys
🌐 Enterprise 360 modules· on Integration 360Browse all 31 views ▾
● LiveBuilt forCOO · Integration PMO· what to cut over nextCFO· unbanked synergyBoard / Wind Point· integration is the value & the risk

Faster integration is Pavion's #1 priority — it is where the deal value is created and where it leaks. This view turns "status" into an executable plan: the 4 in-flight brands, their six workstreams, the blockers in the way, and the ~$151.6M of synergy still unbanked waiting on the cutover.

Data backing: integration_workstream (6 workstreams × in-flight brand, % · owner · target) · integration_blocker (severity · owner · due) · integration_econ (budget · spend · synergy) · synergy_track (program plan vs actual run-rate) · brand_cohort (integration %, status)
Brands in-flight
4
mid-integration
Unbanked synergy
$151.6M
target − realized
Avg integration
67%
across in-flight
Open blockers
8
not yet resolved
Cost-to-integrate ROI
1.2x
synergy ÷ spend
$ still integrating
$4466.55M
4 businesses
Per-brand integration scorecard

Where each in-flight brand stands — and the next move

Do this: work the blocker named in each card first; if none, push the lowest-% workstream to its target date.

Birla Pivot
acquired 2023 · $1570.06M revenue · synergy 74%
In progress
Overall integration82%
ERP / Ledger90%· Done
Customer Master85%· Jul 2026
Quoting / CPQ70%· Sep 2026
Tech Stack / Network88%· Done
Org / Branding95%· Done
Field / Dispatch75%· Aug 2026
Price-book reconciliation: 40 SKUs priced below governed floor; RevOps reviewing. · Ravi Desai · due 2026-09-20
Bay-area crews not yet on common telematics; minor utilization drag. · Field Ops · due 2026-09-30
Next move: Clear the medium on Quoting / CPQ: Price-book reconciliation: 40 SKUs priced below governed floor; RevOps reviewing. (Ravi Desai, due 2026-09-20).
Livaeco
acquired 2024 · $1109.87M revenue · synergy 55%
In progress
Overall integration60%
ERP / Ledger55%· Nov 2026
Customer Master60%· Oct 2026
Quoting / CPQ30%· Q1 2027
Tech Stack / Network65%· Sep 2026
Org / Branding80%· Aug 2026
Field / Dispatch50%· Dec 2026
Legacy estimator has no API; quote history export blocked on vendor — stalls CPQ cutover. · Ravi Desai · due 2026-09-15
Chart-of-accounts mapping unresolved for 3 cost centers; revenue still books region-only (Birmingham 45% coverage). · Sunil Bhatia · due 2026-10-30
Next move: Clear the blocker on Quoting / CPQ: Legacy estimator has no API; quote history export blocked on vendor — stalls CPQ cutover. (Ravi Desai, due 2026-09-15).
Aditya Birla Renewables
acquired 2024 · $1001.59M revenue · synergy 78%
In progress
Overall integration80%
ERP / Ledger85%· Aug 2026
Customer Master78%· Sep 2026
Quoting / CPQ75%· Sep 2026
Tech Stack / Network82%· Done
Org / Branding90%· Done
Field / Dispatch70%· Oct 2026
Tech certs not yet mapped to common dispatch; manual routing in Columbus metro. · Field Ops · due 2026-10-10
Next move: Clear the medium on Field / Dispatch: Tech certs not yet mapped to common dispatch; manual routing in Columbus metro. (Field Ops, due 2026-10-10).
Birla Cellulose
acquired 2024 · $785.03M revenue · synergy 40%
Early
Overall integration45%
ERP / Ledger40%· Q1 2027
Customer Master45%· Dec 2026
Quoting / CPQ20%· Q2 2027
Tech Stack / Network50%· Nov 2026
Org / Branding70%· Oct 2026
Field / Dispatch35%· Q1 2027
~200 duplicate accounts vs golden record need steward review before billing migration. · MDM steward · due 2026-11-30
Site network upgrade gating SOC failover; waiting on circuit provisioning (vendor lead time). · Infrastructure · IT · due 2026-11-15
Next move: Clear the high on Customer Master: ~200 duplicate accounts vs golden record need steward review before billing migration. (MDM steward, due 2026-11-30).
Workstream heatmap

Six workstreams × in-flight brands

Read across each row for the brand's weak spot; read down each column for the workstream that's stuck enterprise-wide. Tint = status; number = % complete.

BrandERP / LedgerCustomer MasterQuoting / CPQTech Stack / NetworkOrg / BrandingField / Dispatch
Birla Pivot90%85%70%88%95%75%
Livaeco55%60%30%65%80%50%
Aditya Birla Renewables85%78%75%82%90%70%
Birla Cellulose40%45%20%50%70%35%
DoneOn trackAt riskBehind
Blocker & risk log

Every thing in the way of a cutover, worst-first

Do this: assign each open blocker a named owner and a date; the Blocker/High rows are the ones holding synergy hostage.

SeverityBrandWorkstreamDescriptionOwnerDueStatus
BlockerLivaecoQuoting / CPQLegacy estimator has no API; quote history export blocked on vendor — stalls CPQ cutover.Ravi Desai2026-09-15Mitigating
HighLivaecoERP / LedgerChart-of-accounts mapping unresolved for 3 cost centers; revenue still books region-only (Birmingham 45% coverage).Sunil Bhatia2026-10-30Open
HighBirla CelluloseCustomer Master~200 duplicate accounts vs golden record need steward review before billing migration.MDM steward2026-11-30Open
MediumBirla CelluloseTech Stack / NetworkSite network upgrade gating SOC failover; waiting on circuit provisioning (vendor lead time).Infrastructure · IT2026-11-15Open
MediumBirla PivotQuoting / CPQPrice-book reconciliation: 40 SKUs priced below governed floor; RevOps reviewing.Ravi Desai2026-09-20Mitigating
MediumAditya Birla RenewablesField / DispatchTech certs not yet mapped to common dispatch; manual routing in Columbus metro.Field Ops2026-10-10Open
Lowrecent acquisitionOrg / BrandingCustomer comms on brand transition pending legal sign-off.Integration PMO2026-08-31Mitigating
LowBirla PivotField / DispatchBay-area crews not yet on common telematics; minor utilization drag.Field Ops2026-09-30Open
Synergy realization vs plan

$522.5M realized vs $649.7M planned · $-127.2M variance

Do this: the negative-variance programs are leaking run-rate — put a 90-day recovery plan on each before they compound into the forecast quarters.

ProgramOwnerPlan $MActual $MVariance% captured
P&C insurance consolidationCFO · Treasury$108.28M$108.28M+$0M
100%
Fleet / auto programProcurement$81.21M$81.21M+$0M
100%
Purchasing / vendor consolidationProcurement$243.63M$189.49M$-54.1M
78%
Systems (CRM / ERP / HR)IT · Sunil Bhatia$162.42M$113.69M$-48.7M
70%
Real estate / office overlapFacilities$54.14M$29.78M$-24.4M
55%
Integration economics

Is it paying back? Blended 1.2x on cost-to-integrate

Do this: protect the ≥1.3x deals as the playbook; for sub-1x deals, freeze discretionary integration spend until synergy capture catches up.

BrandAcquiredBudgetSpentSynergy targetSynergy realizedROIStatus
Livaeco2024$102.87M$56.85M$97.45M$54.14M1.0xIn progress
Aditya Birla Renewables2024$92.04M$70.38M$94.75M$73.09M1.0xIn progress
Birla Cellulose2024$81.21M$32.48M$81.21M$32.48M1.0xEarly
Birla Pivot2023$124.52M$97.45M$146.18M$108.28M1.1xIn progress
UltraTech Cement2022$86.62M$83.92M$135.35M$119.11M1.4xIntegrated
Birla Opus2021$48.73M$46.02M$70.38M$64.97M1.4xIntegrated
Aditya Birla Capital2021$37.9M$35.19M$54.14M$48.73M1.4xIntegrated